【多选题】【消耗次数:1】
We were very tired and wanted to get home ____________________ .
as soon as possible
as quickly as possible
as fast as possible
as much as possible
参考答案:
复制
纠错
相关题目
【单选题】 As a freshman, we should get to know campus ( ) as soon as possible and make good use of them.
①  Source
②  sources
③  resource
④  resources
【单选题】 The assistant wrapped it _____ for her as quickly as possible.
①  round
②  about
③  in
④  up
【单选题】 You had better ________ a doctor as soon as possible.
①  seeing
②  saw
③  see
④  seen
【单选题】 The adviser recommended that Mary _____ the training program as soon as possible.
①  started
②  starts
③  start
④  would start
【单选题】 Our teacher recommended that we _____as attentive as possible when we visit the museum.
①  are
②  shall be
③  be
④  were
【单选题】 Our teacher recommended that we ____ as attentive as possible when we visit the museum.
①  are
②  shall be
③  be
④  were
【单选题】 What are the possible roles of a teacher?
①  Controller, assessor
②  Organizer, prompter
③  Participant, resource-provider
④  All of the above.
【单选题】 Is _____ possible to fly to the moon in a spaceship?
①  now
②  man
③  that
④  it
【单选题】 Our manager will look into the matter as soon as possible. Just have a little ____ after an operation.
①  wait
②  time
③  patience
④  rest
【单选题】 Put up the passbook and the card properly. ______us as soon as possible if you lose them.
①  Reform
②  Inform
③  Transform
④  uniform
随机题目
【多选题】 在工程网络计划的执行过程中,当某项工作进度出现偏差后,需要调整原进度计划的情况有( )。
①  项目总工期不允许拖延,但工作进度偏差已超过其总时差
②  项目总工期允许拖延,但工作进度偏差已超过其自由时差
③  项目总工期允许拖延的时间有限,但实际拖延的时间已超过此限制
④  后续工作不允许拖延,但工作进度偏差已超过其总时差
⑤  后续工作允许拖延,但工作进度偏差已超过其自由时差
【多选题】 固定节拍流水施工的特点是( )。
①  只有一个施工过程在各个施工段流水节拍均相等
②  所有施工过程在各个施工段流水节拍均相等
③  相邻施工过程的流水步距相等
④  各施工段同时开展相同专业的施工
⑤  同一时间内将会有多个专业队施工
【多选题】 在建设工程施工阶段,当通过压缩网络计划中关键工作的持续时间来缩短工期时,通常采取的组织措施有( )。
①  改善劳动条件
②  增加每天的施工班次
③  增加劳动力和施工机械的数量
④  组织搭接作业或平行作业
⑤  缩短工艺技术间隙时间
【单选题】 以专用接地跨接的两卡间边线为铜芯软导线,截面积不小于( )mm<sup>2</sup>。
①  2.5
②  4
③  6
④  10
【单选题】 地漏的水封高度,不得小于( )mm。
①  30mm
②  40mm
③  50mm
④  60mm
【单选题】 空调系统带冷(热)源的正常联合试运转不应少于( )小时。
①  24
②  16
③  8
④  4
【单选题】 给水管道试验压力均为工作压力的( )倍,但不得小于0.6MPa。
①  1
②  1.5
③  2
④  2.5
【单选题】 安装在一般楼板处的套管,其顶部高出装饰地安装在一般楼板处的套管,其顶部高出装饰地20mm即可,而安装在卫生间及厨房内的套管其顶部应高出装饰地面( )mm?
①  30mm
②  40mm
③  50mm
④  60mm
【单选题】 相导体截面积为>16,且≤35,保护导体的最小截面积为( )。
①  16
②  4
③  6
④  10
【单选题】 采用PE管作为市政饮用水管材必须是黑管纵向上至少带( )色条。
①  三条黄色色条
②  三条黑色色条
③  三条红色色条
④  三条蓝色色条