【单选题】【消耗次数:1】
Not only does Tom attend class regularly, but he also ()in extracurricular activities frequently.
participates
participate
involve
involved
参考答案:
复制
纠错
相关题目
【单选题】 _________ the regular classes, you can also attend many different seminars and take part in many extracurricular activities.
①  Except for
②  Including
③  Apart from
④  Included
【单选题】 _________ the regular classes, you can also attend many different seminars and take part in many extracurricular activities.
①  Except for
②  Including
③  Apart from
④  with
【单选题】 Not only are cars involved in most of the traffic accidents, but they also __________to the pollution of the air. .
①  contribute
②  promote
③  refer
④  matter
【单选题】 The reason that his property was confiscated by the country, it _____, was that he was involved in a lot of fraudulent activities during the war.
①  was turned out
②  was being turned out
③  being turned out
④  turned out
【判断题】 A: Tom speaks English very well. B: So he does.
①  正确
②  错误
【简答题】 3. According to his grandparents, what does integrity involve?
【单选题】 Not only the society but also the people in it ______.
①  has changed
②  have changed
③  have been changed
④  has been changed
【单选题】 Not only the teacher but also the students _______ smiling.
①  is
②  are
③  was
④  be
【单选题】 Spitting on the ground is not only ______ but also harmful to others’ health.
①  blasting
②  banging
③  grabbing
④  disgusting
【判断题】 He runs as faster as Tom.
①  正确
②  错误
随机题目
【单选题】 通过不同工期及相应工程费用的比较,寻求与工程费用最低相应的 最优工期的方法称( )
①  工期优化
②  费用优化
③  资源优化
【单选题】 某分部工程有A、B、C、D四个施工过程,6个施工段,流水节拍分别为2天、6天、4天、2天,当组织成成倍流水节拍时,其施工班组数为7个;工期为
①  6个
②  7个
③  22天
④  24天
【单选题】 双代号网络计划中的关键线路是指
①  总时差为零的线路
②  总的工作持续时间最短的线路
③  一经确定、不会发生转移的线路
④  自始至终全部由关键工作组成的线路
【单选题】 不属于流水施工效果的是
①  可以实现达到节约使用资源
②  可以带来良好的施工秩序
③  提高了工人的劳动强度
【单选题】 施工进度控制的主要工作环节包括:①编制资源需求计划;②编制施工进度计划;③组织进度计划的实施;④施工进度计划的检查与调整。其正确的工作程序是
①  ①-②-③-④
②  ②-①-③-④
③  ②-①-④-③
④  ①-③-②-④
【单选题】 关于施工进度计划调整的说法,正确的是
①  当资源供应发生异常时,可调整工作的工艺关系
②  当实际进度计划拖后时,可缩短关键工作持续时间
③  为充分利用资源,降低成本,应减少资源的投入
④  任何情况下均不允许增减工作项目
【单选题】 自由时差是指各项工作在不影响紧后工作( )的条件下所具有的机动时间
①  最迟开始时间
②  最早开始时间
③  最迟完成时间
【单选题】 资源优化的方法是通过改变工作的( ),使资源按时间的分布符合目标
①  开始时间
②  结束时间
③  持续时间
【判断题】 网络计划工期调整的方法,就是缩短某些工作的持续时间。
①  正确
②  错误
【判断题】 网络计划的工期优化,就是通过压缩某些关键工作的持续时间,以达到缩短工期的目的。
①  正确
②  错误