在共同延误的情况及责任划分中,初始事件原则下图表述正确的是()。(图中各符号的含义如下:C代表承包商;E代表业主;N代表大自然或客观原因;代表不可补偿;=代表可补偿工期;≡既可工期延长又可费用补偿)
①
<imgwidth="111"height="70"src="../uploadfiles/word/gcsp002.files/image001.png">
②
<imgwidth="130"height="81"src="../uploadfiles/word/gcsp002.files/image002.png">
③
<imgwidth="126"height="79"src="../uploadfiles/word/gcsp002.files/image003.png">
④
<imgwidth="113"height="81"src="../uploadfiles/word/gcsp002.files/image004.png">